Interim valuations in construction explained

Guide · checked 2 November 2026

On most building contracts the contractor is paid in instalments as the work progresses rather than in one sum at the end. Each instalment follows an interim valuation of the work done. The Housing Grants, Construction and Regeneration Act 1996 gives a party to a construction contract the right to payment by instalments, stage payments or other periodic payments, unless the work is specified in the contract as lasting less than 45 days. JCT contracts set out their own valuation and payment cycle, so check your own contract.

The interim payment cycle

  1. Application: the contractor submits an application setting out the sum it considers due, usually before the valuation date.
  2. Valuation: the quantity surveyor values the work at the valuation date.
  3. Payment notice or certificate: the payer, or a specified person, gives a payment notice within five days of the payment due date (s.110A). On many JCT forms an interim certificate does this job.
  4. Pay less notice: if the payer intends to pay less than the notified sum, it must give a pay less notice in time (s.111).
  5. Payment: the notified sum, or the amount in a valid pay less notice, is paid by the final date for payment.

What goes into an interim valuation

Deductions

VAT is added where it applies. For CIS-registered payments between VAT-registered businesses, the VAT domestic reverse charge may apply; see CIS and the domestic reverse charge explained.

A simple worked example

Item£
Work done to date180,000
Preliminaries to date24,000
Variations to date8,500
Materials on site6,000
Gross valuation218,500
Less retention at 3%(6,555)
Less previously certified(162,000)
Net due this period (before VAT)49,945

Figures are invented for illustration. The retention percentage and what may be included are set by your contract.

Who carries out the valuation

On traditional JCT contracts the quantity surveyor usually values the work and the architect or contract administrator issues the interim certificate. On Design and Build contracts the contractor's application and the employer's response follow the procedure set out in that contract. Subcontract valuations follow the subcontract. Check your own contract for who does what and by when.

If the amount is disputed

Section 108 of the Act gives a party to a construction contract the right to refer a dispute to adjudication at any time, including a dispute about an interim valuation. Separately, if the notified sum is not paid by the final date and no valid pay less notice was given, section 112 gives the payee the right to suspend performance after at least seven days' notice.

Good records

Sources

Templates for this task

Check before use – not legal advice. This guide states the law and official guidance as facts, in our own words, as checked on 2 November 2026. It does not replace professional advice on a specific matter. Contains public sector information licensed under the Open Government Licence v3.0.